9 December 2013

Welcome to Council's coastal update.

Please feel free to pass on this e-news to people you believe may be interested in coastal matters.  They can also subscribe to the e-news at the end of the email.

New Brighton Beach scraping - Commenced in November

Council undertook beach scraping works from 11 November to 2 December 2013. The works extended approximately 1.3 km from the beach access at North Head Road to the Park Street beach access at Kendall’s Groyne, New Brighton. Dune re-vegetation works are to commence on the 4 December 2013.

A report will be tabled in the New Year that examines the success of the works in terms of project objectives. These objectives include improving beach access and amenity and increasing the sand volume in the foredune to provide a greater short term buffer against coastal erosion and inundation at this location.

The photos below provide an indicative illustration of ‘before’ and ‘after’ Beach Scraping Works along New Brighton Beach.

Figure 1 - Before beach scraping works - New Brighton 2013

Figure 2 - After beach scraping works - New Brighton 2013

More information on the project can be found on Council’s website at: http://www.byron.nsw.gov.au/new-brighton-beach-scraping

This project is supported by the NSW Government’s Coastal Management Program.



Investigating the Re-design of the Jonson Street Protection Works

The draft final report has been reviewed by Council staff and state agencies and is expected to be tabled at the 6 February 2014 Ordinary Meeting.

More information on the project can be found on Council’s website at:

http://www.byron.nsw.gov.au/investigating-the-re-design-of-the-jonson-street-protection-works-byron-bay

This project is supported by the NSW Government’s Coastal Management Program.